Neumann Petroleum installed a 4.6km underground pipeline from their terminal in Whinstanes to the Common User Wharf at Eagle Farm in Brisbane, constructed using both trenching and Horizontal Directional Drilling (HDD) methods. Part of these works included new fire system installation complete with fire pumps and fire monitors at the wharf; marine fuel unloading arms; terminal pipe work upgrade complete with an automated pig receiver system; and all associated electrical, civil and mechanical works. TfA provided the detailed design, project management of the project and all statutory approvals, quality assurance and construction assistance for the entire project.